Major Projects
On-going Projects
Generation
There are presently three major hydroelectric
projects under construction. While these
projects are primarily aimed for export, only
the surplus power generated is exported after
meeting the domestic demand.
Tala Hydroelectric Project
This project is scheduled for completion in the
year 2005/2006 with an installed capacity of
1020 MW and an annual generation of 4865 Million
Units. The project is financed by the Government
of India with a financing mix of bilateral
assistance and soft loan. This project is the
largest high-head (860m) power plant being
constructed in the region.
Kurichu Hydroelectric Project
This project is scheduled for completion by 2002
with an installed capacity of 60 MW and an
annual generation of 400 Million Units.
Generation from three units (out of four)
started from October 2001 and it has started
supplying power to six dzongkhags in eastern
Bhutan and two dzongkhags in south-central
Bhutan. Surplus power is being exported to India
through the 132 kV Gelephu-Salakati line. The
project is financed by a combination of
bilateral assistance and soft loan from the
Government of India.
Basochu Upper Stage Hydropower Project
This project has an installed capacity of 22.2
MW with an annual generation of 105 Million
Units. The project has been commissioned and
will be completed by December 2001. This project
has helped to augment the generation supply in
western Bhutan as well as improve the
reliability of power supply in the region. The
project is financed by the Austrian Government
under a financing mix of bilateral assistance
and soft loan.
Basochu Lower Stage (Rurichu) Hydropower Project
A turn-key project agreement was signed on
September 13, 2001 between the Royal Government
of Bhutan and Austrian Hydro Consortium Basochu
(AHCB) for the lower stage of the Basochu
project. This second stage will have an
installed capacity of 40 MW with an annual
energy generation of 186 Million Units, and is
expected to be completed within 36 months. The
project is financed under Official Austrian
Export Promotion Scheme Loan. The project
construction is scheduled to start from January
2002.
Re-commissioning/refurbishing of mini hydels
Rehabilitation of eight mini hydels built
between 1966-1988 started from the Seventh Five
Year plan and is scheduled for completion by
December 2002. Most of the rehabilitated
stations are connected to the main grid.
The Kellungchu Valley Project (Rongchu Micro
Hydel) in Thimyul, Lhuentse
A 200 kW micro hydel station has been built in
Thimyul across the Rongchu tributary of Kurichu
in Lhuentse. The project was conceived under the
Activities Implemented Jointly between the Dutch
Ministry of Environment, Netherlands & the Royal
Government of Bhutan. The project will electrify
around 130 households in and around Kellungchu
valley. The work on the project has been
completed and is scheduled for inauguration on
December 17, 2001.
Transmission
Works are in progress to extend the transmission
lines from the on-going mega hydroprojects or
the existing plants to as many dzongkhags as
possible. The major transmission lines under
construction (or near completion) are described
below.
Eastern Transmission Grid
The Eastern Transmission Grid is being developed
to evacuate power from the 60 MW Kurichu
hydroelectric project to six districts in
eastern Bhutan and two districts in south
central Bhutan. Surplus power from the project
is to be exported through south central Bhutan.
A total distance of 262 km long 132 kV grid
network has been completed during the Eight Five
Year plan with six major transmission
substations to distribute power to the various
load centers. The 48 km long transmission line
to Lhuentse and the substation at Tangmachu will
be completed in the begining of the Ninth Five
Year plan. The project is financed by the
Government of India through bilateral
assistance.
Western Transmission Grid (220 kV
Semtokha-Basochu Transmission line)
In Western Bhutan, 23 km long 66 kV transmission
line from Lobesa to Basochu Upper Stage has been
completed. For the 220 kV Semtokha-Basochu
Transmission line, construction work is about to
be started.
Rural Electrification
Under the Power Distribution programme, 6211
additional consumers (till December 2000) have
been added to the system during the Eight Five
Year plan. Extensive rural electrification works
have been carried out in about 189 villages in
the Dzongkhags of Ha, Samdrupjongkhar,
Trashigang, Trashiyangtse, Chukha, Thimphu,
Punakha, Wangdue, Paro and Lhuentse. About 80%
of the work has been completed for further rural
electrification of an additional 6028 households
in various dzongkhags under the Second ADB Rural
Electrification Project. Works have also started
to electrify additional 388 households in
Dungkhar, Chungkha and Zhemgang under SDP
(Sustainable Development Project) funding from
the Netherlands.
Solar electrification of remote schools, basic
health units and community centers in the
various dzongkhags is also being carried out.
About 50 solar sets are being provided to each
dzongkhag under Dutch assistance. Under the
sustainable rural electrification loan project
from ADB, 20 households will be electrified. A
Dutch bicycle campaign organized by an NGO
contributed about Nu.1,600,000 for solar
electrification of Singkhar Lori in Samdrup
Jongkhar.
Electricity Act
The Asian Development Bank has been providing
technical assistance for the restructuring of
power sector and corporatisation of the utility
functions of the Department of Power. The
corportisation is scheduled from July 2002. The
National Assembly of Bhutan has approved the
Electricity Act 2001 in the 79th session on July
26, 2001.
Top of Document
Future
Projects
Generation
Feasibility Study of Mangdechu Hydroelectric
Project
The feasibility study of the Mangdechu Project
under the NORAD/Norwegian Government funding has
been completed. The study has found that a hydro
power project of 360 MW capacity across the
Mangdechu in Trongsa dzongkhag is feasible. The
project construction investment is planned in
the Ninth Five Year plan and it is expected to
be completed in the Tenth Five Year plan.
Feasibility Study of Punatsangchu Project
The feasibility study of the Punatsangchu
hydroelectric project in Wangdephodrang
dzongkhag under the Japan Government technical
assistance has been completed. The study has
found that a hydro power project of 870 MW
capacity is feasible. The project construction
investment is planned in the Ninth Five Year
plan and it ia expected to be completed in the
Tenth Five Year plan.
Feasibility Study of Micro Hydels
Under the UNDP/GEF feasibility project, four
micro hydel sites have been identified as
feasible at Sengor (Mongar), Sakten (Trashigang),
Tang (Bumthang) and Gasa. However, in the Ninth
Five Year plan only three sites viz. Sengor,
Sakten and Tang are planned for implementation.
For electrification of Gasa, grid extension from
Punakha is planned.
Transmission
The major transmission projects planned are
listed below:
132 kV/33 kV Tintibi-Trongsa/Bumthang
Transmission line and substations
220/132/66/33 kV Basochu-Tsirang/ Dagana-Gelephu
lines and substations
Top of Document